Calculators and formulas for critical communications
Quick checks we use on remote radio and comms site design: RF conversions, path loss and link budgets, cable voltage drop and off-grid solar sizing with Bureau of Meteorology solar data for Western Australia. Everything runs in your browser.
Power, frequency and matching
Convert between the units that turn up on radio datasheets and test sheets.
Power: dBm, watts and dBµV
Enter a power in any unit.
Formulas
dBm = 10·log₁₀(P / 1 mW)dBW = dBm − 30V = √(P·Z) dBµV = 20·log₁₀(V / 1 µV) (50 Ω: dBµV = dBm + 107)Frequency and wavelength
Wavelength and antenna element lengths.
Velocity factor 0.95 is a typical starting point for a wire or tube element; use the cable's VF for coax stubs. Trim to the antenna manufacturer's chart.
Formulas
λ (m) = 299.792458 / f (MHz)physical length = fraction × λ × VFVSWR, return loss and mismatch
Enter any one value from your sweep.
Formulas
|Γ| = (VSWR − 1) / (VSWR + 1) = 10^(−RL/20)RL (dB) = −20·log₁₀|Γ|Mismatch loss (dB) = −10·log₁₀(1 − |Γ|²)EIRP and ERP
Radiated power from transmitter power, feeder loss and antenna gain.
Take feeder loss per 100 m at your operating frequency from the cable datasheet.
Formulas
EIRP (dBm) = P_tx (dBm) − losses (dB) + G (dBi)ERP (dBm) = EIRP − 2.15 (dBi = dBd + 2.15)Will the link close?
Line-of-sight estimates for UHF, VHF and microwave paths. Real paths need a terrain profile, but these numbers tell you quickly whether a link is worth surveying.
Free space path loss and link budget
Defaults are a 25 W UHF DMR repeater talking to a mobile 30 km away.
Free-space range ignores the earth's curvature, so compare it with the radio horizon below. Use "other losses" for things free space doesn't cover: foliage, building penetration, body loss, diffraction over terrain. Free space is a best case.
Formulas
FSPL (dB) = 20·log₁₀(d km) + 20·log₁₀(f MHz) + 32.44Rx level = P_tx − L_tx + G_tx − FSPL − L_other + G_rx − L_rxFade margin = Rx level − Rx sensitivityFresnel zone and earth bulge
Clearance needed at a point along the path, such as an obstacle.
Last value = bulge + 60% of the first Fresnel zone. Add it to the obstacle height to get the minimum beam height at that point. k = 4/3 is standard atmosphere. Check k = 2/3 for critical microwave paths.
Formulas
r₁ (m) = 17.32·√(d₁·d₂ / (f GHz · D)) (d in km)h_bulge (m) = d₁·d₂ / (12.74·k)Radio horizon
Line-of-sight range between two antennas over smooth earth.
Formulas
d (km) = 3.57·√(k·h) (h in m; 4.12·√h for k = 4/3)d_total = d₁ + d₂Cable voltage drop by conductor size
Size DC supply runs to radios, repeaters and comms huts, or check AC sub-circuits. Results are listed for every common copper size, with the smallest compliant cable highlighted.
| Copper size | R (Ω/km) | Drop (V) | Drop (%) | Max length (m) |
|---|
Resistive drop only, for copper conductors. On larger AC cables, reactance adds a few percent, so check final AC designs against AS/NZS 3008.1.1. AS/NZS 3000 generally limits drop to 5% from the point of supply to any point in the installation. For DC radio supplies, also check the radio's minimum operating voltage at end-of-discharge battery voltage.
Formulas
R_T = (ρ₂₀ / A)·(1 + 0.00393·(T − 20)) ρ₂₀ = 0.017241 Ω·mm²/mDC and single-phase: V_d = 2·L·I·R_T three-phase: V_d = √3·L·I·R_TMax length = (V_d,max) / (2·I·R_T) (or √3 for three-phase)Solar and battery sizing for remote sites
Size a solar array and battery bank for a repeater or comms hut. The calculator uses the Bureau of Meteorology's 1990–2019 average daily solar exposure for the nearest location below, adjusts it to your panel tilt, and sizes for the worst month.
| Month | BOM horizontal (MJ/m²/day) | Peak sun hours, horizontal | Peak sun hours, tilted | Array output (kWh/day) | Load (kWh/day) |
|---|
Array derating covers temperature, dust, cable losses, MPPT and battery charge efficiency. 75% is a reasonable figure for hot, dusty northern sites. Design margin is added to the load. For lead-acid, use 50% depth of discharge or less. Check the battery's temperature derating for unconditioned huts.
Method and formulas
Peak sun hours (h) = H (MJ/m²/day) / 3.6H_T = H_b·R_b + H_d·(1 + cos β)/2 + H·ρ·(1 − cos β)/2 (ρ = 0.2)H_d/H from the Erbs monthly correlation with K_T = H / H₀, at Klein's mean day for each monthArray (W) = E_day·(1 + margin) / (PSH_T,worst·derating)Battery (Ah) = E_day·(1 + margin)·days / (V·DoD)Isotropic-sky tilt model (Liu and Jordan) after Duffie and Beckman, Solar Engineering of Thermal Processes. Panels are assumed to face true north.